Lane Closures Begin in Late October

The Wentzville Parkway Turn Lane Project is underway. Lane closures will be necessary beginning next Tuesday. To view a map of the work zone, please click here.

Beginning the morning of Tuesday, Oct. 29, a westbound left-lane closure (starting east of Meyer Road) will be necessary in order to remove the raised concrete island near the Walgreens entrance. This is required for traffic staging during the pavement replacement and widening stage. Later Tuesday afternoon, the lane drop will be switched to the right lane for pavement replacement and widening. The lane drop will remain in place permanently until the widening is completed. The lane closure will run from Meyer Road to Schroeder Creek Boulevard. This project is ongoing through the spring of 2020.

 