West Meyer Road Phase III
West Meyer Road Phase III
Project Status:
January 27, 2017: City of Wentzville entered into an agreement with Oates Associates (Designer) for consultant/professional services for West Meyer Road Phase III.
January 31, 2017: City of Wentzville issued Oates Associates Notice to Proceed to begin design work for West Meyer Road Phase III.
February 3, 2017: Land Survey Notifications sent out to residents in the area for notification that surveyors would be in the area gathering information.
March 2017: Designer began working on conceptual plans
September 2017: Designer began working on preliminary plans and right of way plans and expect to submit to City for review in early 2018.
2018
February 9,2018: City sent out 60-Day Right-of-Way (ROW) notification letters and donation letters to affected properties.
Consultant design engineer Oates Associates has submitted Priliminary Plans and ROW plans and is continuing to work toward 70% plan submittal in spring 2018 and final plan submittal fall 2018.
February 22,2018: Utility Coordination meeting scheduled, with necessary utility relocations to take place later in 2018, after ROW is acquired.
March 15, 2018: Public Meeting tentatively scheduled for this date at Wentzville City Hall. (formal notice will go out soon)