David Hoekel Parkway Phase 2

Project Description- David Hoekel Parkway Phase 2 ABC -  North Outer Road & I-70/David Hoekel Parkway Interchange Grading Project.

The project consists of the construction of a relocated North Outer Road, new MSE wall and grading for the future Interstate 70 and David Hoekel Parkway interchanged including: paving, concrete sidewalk, concrete curb ramps, paved approaches, pavement markings, lighting, ITS, MSE Wall and outer appurtenances.

Fall 2019- North Outer Road open to traffic and porject substantially complete.

Project Description- David Hoekel Parkway Phase 2 ABC -   I-70/David Hoekel Parkway
Interchange Project.

The David Hoekel Parkway & Interstate 70 Interchange Project shall consist of grading of
eastbound ramps, construction of bridges over Interstate 70 and the Norfolk Southern Railroad,
and paving of David Hoekel Parkway and interchange ramps.

April 2020 –
Project Awarded to Lehman Construction LLC.

June 2020 –
Work began on Eastbound I-70 with Temporary Barrier Wall and Storm Sewer
Installation.

August 2020 –
Submittal and Approval of MSE Wall Shop Drawings to begin production of
precast concrete panels and steel reinforcement components.

Full Interchange anticipated to be completed by Fall 2021.
 
For question regarding this project please contact Tony Gambaro, Senior Project Manager
at Anthony.Gambaro@wentzvillemo.org









bg

Stay Up to Date
Sign up for our eNewsletter