Project Description:

The project will consist of adding a center turn lane, ADA compliant sidewalks and trails, upgraded storm water system and associated utility relocations on Wentzville Parkway between Schroeder Creek Blvd and Meyer Road.

Project Location:

Wentzville Parkway between Meyer Road and Schroeder Creek Blvd

Project Status:

  •  April 2017 – City entered into an agreement with Thouvenot, Wade & Moerchen, Inc (TWM)for consultant / professional services for the design of Wentzville Parkway Turn Lane Phase 2
  • May 2017 – Notice to was issued for the design of Wentzville Parkway Turn Lane Phase 2

  • June 2017 – EFK Moen completed the survey work. TWM also completed the 3D scans of the intersections at Meyer Road and Schroeder Creek Blvd. Conceptual Plans were started by TWM.

  • September 2017 – TWM began working on Preliminary Plans.
  • November 2017 – Geotechnical subcontractor collected boring samples within the project limits. TWM continues work on Preliminary Plans, Right of Ways Plans and documents.